Jackson County JD 31

Search

Location: Sections 8, 9, 10, 15, 16, 17, 18, 19, 20, 29 and 30 of West Heron Lake Township

Size: 4.1 square miles

Project: Construction of an open ditch system generally following the route of the main tile system across Sections 17 and 20 of West Heron Lake Township. Proposed laterals replaced the function of themain tile across portions of Sections 19 and 20 and replaced the function of Branch 7 across protions of Sections 17 and 18.

Cost:$1,380,000.00; financed by general obligation bonding through Jackson County

Status: Project is completed. Final Acceptance Hearing was held on January 21, 2015.

We use cookies on our website. Some of them are essential for the operation of the site, while others help us to improve this site and the user experience (tracking cookies). You can decide for yourself whether you want to allow cookies or not. Please note that if you reject them, you may not be able to use all the functionalities of the site.