Overall Goal: Increase landowner awareness of J-hook weirs, unique streambank stabilization structures, through installation at one site on Jack Creek and one site on Okabena Creek and increase public awareness and ownership of water quality problems through printed media and a mailing.
Project Goal 1: Implementation of two streambank restoration projects using J-hook weirs.
Project Goal 2: Increase ownership of water quality problems through an informative mailing targeted to landowners along Jack and Okabena Creeks.
Project Goal 3: Provide educational opportunities through publication of a newsletter and newspaper article to inform the public about the project.
- Funded through the EPA Section 319 grant program administered by the MPCA
- Timeframe – October 1, 2012 to August 31, 2016
- Grant funds - $20,600.00
- Inkind match (HLWD and partners) - $21,184.00
- Total project cost - $41,784.00
Documentation:
Jack Creek Project Photos
August 2013
May 14,2014
June 5, 2014
July 1, 2014
August 4, 2014
May 21, 2015
June 9, 2015
July 20, 2015
August 10, 2015
September 2, 2015
May 23, 2016
June 6, 2016
July 18, 2016
August 01, 2016
Jack Creek Project Videos
Okabena Creek Project Photos
May 19, 2014
May 21, 2015
June 8, 2015
July 20, 2015
August 10, 2015
September 2, 2015
Construction September 22, 2015
May 24, 2016
June 6, 2016
July 18, 2016
August 01, 2016
Okabena Creek Project Videos